Fictional business, figures and margins. The percentages here measure what remains after the modeled direct project costs.
Recommendation
Define the scope before you quote.
Keep the $24,000 quote for the original scope if the cost estimate holds. If the extra work is in scope and expected direct costs are $19,800, the quote would need to reach $26,400 to meet the owner’s 25% target.
What happens when the work expands?
At $24,000, the owner’s 25% target allows up to $18,000 in direct project costs.
| Option | Direct costs | Margin |
|---|---|---|
| Original scope at $24,000 | $16,800 | 30% |
| Extra work included at $24,000 | $19,800 | 17.5% |
| Extra work included at $26,400 | $19,800 | 25% |
What the figures assume
- Extra revisions and coordination add $3,000 in direct labor and vendor costs.
- We calculate direct project margin as price minus direct costs, divided by price. Company overhead and taxes sit outside this illustration.
- The $26,400 figure is the price required under these assumptions. The client’s willingness to pay is a separate question.
What would change the call?
Confirm the labor estimate and the scope the client expects. If the expanded scope cannot command the required price, offer a narrower scope, agree on a separate price for extra work, or reconsider the job.